Question: Please solve the question 2 Given the information in the table, how many weeks activity C could be delayed without delaying the ?completion time of

Please solve the question
2 Given the information in the table, how many weeks activity C could be delayed without delaying the ?completion time of the project (2) activity B Immediate Optimistic predecessors Time (weeks) None 2. A 4 A 2 B 4 D 8 2. EF 2 G 1 Most likely Time (weeks) 4. 6 3 7 10 5 2 22 Pessimistic Time (weeks) 6 8 4 10 12 8 2. 3Step by Step Solution