Question: Please solve this problem ASAP Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the

Please solve this problem ASAP
Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the Earliest due date (EDD) rule is used? Calculate 1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center. Job P Q Process Time At This Operation (hrs) 6 10 5 8 6 Process Time At Remaining Operations (hrs) 4 15 10 12 8 Final Due Date (hrs) 8 40 30 S T 45 24 Average flow time Flow time Number of jobs Days tardy Average job tardiness = Number of jobs Flow time Average number of jobs at the center = job timesStep by Step Solution