Question: Please solve this question for me . QUESTION 2 The Table below shows specic activities and their dependency: Activity Duration (Days) Dependency 2 Start 2
Please solve this question for me .

QUESTION 2 The Table below shows specic activities and their dependency: Activity Duration (Days) Dependency 2 Start 2 A ( B will start after A) 1 A (C will start after A) 4 B (D will start aer B) 2 C (E will start after (3) D and E (F will start after D &E) amorous} 2.1 Use this information to draw a CPM neMork diagram. (16) 2.2 Identify the critical path (N B! Show your workings). (4)