Question: Please solve this question. Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC,

 Please solve this question. Using the following data to do the

Please solve this question.

Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC, ETC. Report whether the project at the end of September is under budget and on schedule or not. Implement formula calculations in Excel and construct EV, PV and AC cumulative graph, and a performance indices (SPI and CPI) graph. (10 points) Month PV AC EV May $120,000 $120,000 $120,000 June $192,000 $215,000 $170,000 July $192,000 $192,000 $173,000 $192,000 $216,500 $190,000 August September $192,000 $170,000 $185,000 October $60,000 Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC, ETC. Report whether the project at the end of September is under budget and on schedule or not. Implement formula calculations in Excel and construct EV, PV and AC cumulative graph, and a performance indices (SPI and CPI) graph. (10 points) Month PV AC EV May $120,000 $120,000 $120,000 June $192,000 $215,000 $170,000 July $192,000 $192,000 $173,000 $192,000 $216,500 $190,000 August September $192,000 $170,000 $185,000 October $60,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!