PLEASE SOLVE USING RCODE/AMPL/CPLEX ONLY

Given the above VSM, under the following operating conditions:
- Hours per shift: 8
- Break minutes per shift: 30
- Break Number per Shift: 2
- Shifts per day: 3
- Days per week: 5
- Weekly Demand = 10,500 units
- Shipping per Day: 1
Calculate and/or Answer :
- Takt Time and
- Is the process able to meet Customer Demand?
- Calculate the Process Cycle Efficiency (PCE)
- Is the PCE conform to the World Class Benchmarks
- If no, calculate the PLT target to meet this threshold
- Propose the necessary Kaizen bursts needed
type the answer
Annual Production Plan Metallservice Weekly Recieving Milling 5 Days C/T = 2 min C/O = 60 min Uptime = 74% 5 days 10 days 2 min. Note: C/T = Cycle Time; C/0= Changeover Time Weekly Delivery Schedule Weekly Schedule Daily Schedule Welding C/T = 5 min C/O = 45 min Uptime = 70% 5 min. Production Control 12 days Daily Schedule Market Forecast Painting C/T = 7 min C/O = 40 min Uptime = 55% 7 min Daily Schedule 8 days Customer Daily Assembly & Inspection 3 C/T =3 min C/O = 35 min Uptime = 95% 2 min. Shipping 30 days 30 days Total Lead Time-65 Days Value Added Time-17 minStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts