Question: Please someone help! very need help with this!!!!!!!!!!!!!!!!!!!!! What is the normal duration of the project: 20 21 22 23 24 25 Q2: What is

Please someone help! very need help with this!!!!!!!!!!!!!!!!!!!!!
What is the normal duration of the project:
| 20 | 21 | 22 | 23 | 24 | 25 |
Q2: What is the early start of B?
| 0 | 3 | 4 | 7 | 11 | 15 |
Q3: What is the early start of C?
| 0 | 3 | 12 | 13 | 17 | 25 |
Q4: What is the early finish of F?
| 10 | 11 | 12 | 13 | 14 | 15 |
Q5: What is the late start of A?
| 0 | 3 | 4 | 7 | 11 | 15 |
Q6: What is the late finish of E?
| 11 | 12 | 13 | 20 | 21 | 22 |
Q7: What is the float of A?
| 0 | 1 | 2 | 3 | 4 | 5 |
Q8: what is the flaot of C?
| 0 | 1 | 2 | 3 | 4 | 5 |
Q9: what is the flaot of H?
| 0 | 1 | 2 | 3 | 4 | 5 |
Q10: What is the crashing cost per day of task A?
| N/A | 150 | 250 | 350 | 400 | 600 |
Q11: What is the crashing cost per day of task C?
| N/A | 150 | 250 | 350 | 400 | 600 |
Q12: What is the crashing cost per day of task E?
| N/A | 150 | 250 | 350 | 400 | 600 |
Q13: Which task should you crash in priority?
| A | B | C | D | E | F | G | H | I |
Q14: What is the duration of the project if all the critical tasks are crashed?
| 16 | 17 | 18 | 19 | 20 | 21 |
Q15: What is the crashing cost of the project if the duration is reduced by 3 days?
| 250 | 800 | 1000 | 1400 | 2000 | 2700 |
Q16: If the penalty is 410 per day and the expected delivery date is day 21, considering there are no other constraints, how many days should you crash?
| 0 | 1 | 2 | 3 | 4 | 5 |
0 online.monaco.edu Firal Ayam Search Textbook Solutions | Chegg.com C Cat Homework Help With Chagg Study | Chegg.com 1 Normal Crashed Crashed Activity Duration Pred. CP Cost Cost Duration A 3 Yes 500 900 2 4 No 800 1400 3 | 5 F Yes 1300 1800 3 D 5 B No 950 1150 4 E 1 D.C No 250 250 F 9 Yes 3150 4200 6 G 4 C Yes 1600 1900 3 H 2 C No 500 500 2 3 E,G,H Yes 675 675 Summ: 9725 12775 Based on the data provided, please answer to the various questions bellow. Prices are given in and durations in days. Help: for this exercise, you should first calculate the logical diagram then the PERT+CP
Step by Step Solution
There are 3 Steps involved in it