Question: Please someone help! very need help with this!!!!!!!!!!!!!!!!!!!!! What is the normal duration of the project: 20 21 22 23 24 25 Q2: What is

Please someone help! very need help with

Please someone help! very need help with this!!!!!!!!!!!!!!!!!!!!!

What is the normal duration of the project:

20 21 22 23 24 25

Q2: What is the early start of B?

0 3 4 7 11 15

Q3: What is the early start of C?

0 3 12 13 17 25

Q4: What is the early finish of F?

10 11 12 13 14 15

Q5: What is the late start of A?

0 3 4 7 11 15

Q6: What is the late finish of E?

11 12 13 20 21 22

Q7: What is the float of A?

0 1 2 3 4 5

Q8: what is the flaot of C?

0 1 2 3 4 5

Q9: what is the flaot of H?

0 1 2 3 4 5

Q10: What is the crashing cost per day of task A?

N/A 150 250 350 400 600

Q11: What is the crashing cost per day of task C?

N/A 150 250 350 400 600

Q12: What is the crashing cost per day of task E?

N/A 150 250 350 400 600

Q13: Which task should you crash in priority?

A B C D E F G H I

Q14: What is the duration of the project if all the critical tasks are crashed?

16 17 18 19 20 21

Q15: What is the crashing cost of the project if the duration is reduced by 3 days?

250 800 1000 1400 2000 2700

Q16: If the penalty is 410 per day and the expected delivery date is day 21, considering there are no other constraints, how many days should you crash?

0 1 2 3 4 5

0 online.monaco.edu Firal Ayam Search Textbook Solutions | Chegg.com C Cat Homework Help With Chagg Study | Chegg.com 1 Normal Crashed Crashed Activity Duration Pred. CP Cost Cost Duration A 3 Yes 500 900 2 4 No 800 1400 3 | 5 F Yes 1300 1800 3 D 5 B No 950 1150 4 E 1 D.C No 250 250 F 9 Yes 3150 4200 6 G 4 C Yes 1600 1900 3 H 2 C No 500 500 2 3 E,G,H Yes 675 675 Summ: 9725 12775 Based on the data provided, please answer to the various questions bellow. Prices are given in and durations in days. Help: for this exercise, you should first calculate the logical diagram then the PERT+CP

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!