Question: PLEASE STEP BY STEP ANSWER A company has a CONWIP-controlled assembly line with three machines: 1,2,3. The process is sequential with the products arriving one
PLEASE STEP BY STEP ANSWER

A company has a CONWIP-controlled assembly line with three machines: 1,2,3. The process is sequential with the products arriving one at a time by conveyor. If there is only one container in the system, the expected flowtimes at machines 1 and 3 are 1.30 and 0.60 minutes, respectively. In addition, the system relative throughput is 0.256 in this case. What is the minimum number of containers needed for the bottleneck machine to work all the time? a. 4 b. 2 c. 3 d. 6 e. 5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts