Question: Please take a look at task #5, 6 , 7, and How much is the duration in days for the Task #5 if its sub
Please take a look at task #5, 6 , 7, and
How much is the duration in days for the Task #5 if its sub tasks 6 & 7 can be done in the same day? and how can I represent that in this chart. would I put Task# 6 & 7 duration of 0.5? But that wouldn't make sense as the criteria for the duration is "(days)".
How would I display these tasks 6 and 7 being done in parallel for this type of chart?
Thank you friend.