Question: please use MRP Table for answer! Chapter 6 problem (please use the MRP table for your answer) 4. Consider the bill of material for Product
please use MRP Table for answer!
Chapter 6 problem (please use the MRP table for your answer) 4. Consider the bill of material for Product and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule (net requirement). J Ha K(1) L (4) M (2) Scheduled receipts Item J K L M Lead Time 1 2 2 1 Quantity on Hand 10 10 0 30 40 in week 2 15 in week 1