Question: Please, use the network diagram and resource loading chart to develop a resource-constrained schedule to see how long the project will take with only two
Please, use the network diagram and resource loading chart to develop a resource-constrained schedule to see how long the project will take with only two resource units.
Be sure to record the order in which you schedule the activities using the scheduling heuristics (rules of thumb): 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number

Using your computations in the previous question, what is the new project duration?
2 B3 2 2 2 4 1 5 7 E 8 2 2 2 9 1 10 0 A 2 020 0 22 5 D 7 0 2 0 5 2 7 10 G 12 0 2 0 102 12 2 c5 0 2 0 2 35 7F 10 0 1 0 7 3 10 ES ID EF SL RES SL LS DUR LF 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 2 B 2 2 2 2 0 2 2 Resource loading chart ID RES DUR ES LF SL - 1 - A 2 2 0 2 0 2 2 1 2 5 2 2 3 2 5 22 570 E 2 1 7 10 2 F 1 3 7 10 0 2 2 10 120 Total resource load 2 2 D 2 2 2 F 1 1 1 2 2 N 4 2 2 2 2 3 1 1 2 2 ID RES DUR ES LF SL 0 - 1 - 2- 3- 4- 5- 6- 7 8 - 9 - 10 - 11 - 12 - 13 - 14- 15 2 2 0 2 0 B 2 1 2 5 2 Ic 2 13 2 5 0 D 2 2 5 7 0 E 12 1 7 10 2 F 1 3 7 10 10 G 2 12 10 12 O Total resource loado 0 0 0 0 0 0 O 0 0 0 O 0 0 o Resource available2 12 12 12 12 12 12 12 12 12 12 12 12 12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts