Question: Please, use the network diagram and resource loading chart to develop a resource-constrained schedule to see how long the project will take with only two
Please, use the network diagram and resource loading chart to develop a resource-constrained schedule to see how long the project will take with only two resource units.
Be sure to record the order in which you schedule the activities using the scheduling heuristics (rules of thumb): 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number
- Use this table to develop a resource-constrained schedule to see how long the project will take with only two resource units.
| ID | RES | DUR | ES | LF | SL | 0 - 1 | - 2 | - 3 | - 4 | - 5 | - 6 | - 7 | - 8 | - 9 | - 10 | - 11 | - 12 | - 13 | - 14 | - 15 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A | 2 | 2 | 0 | 2 | 0 | |||||||||||||||
| B | 2 | 1 | 2 | 5 | 2 | |||||||||||||||
| C | 2 | 3 | 2 | 5 | 0 | |||||||||||||||
| D | 2 | 2 | 5 | 7 | 0 | |||||||||||||||
| E | 2 | 1 | 7 | 10 | 2 | |||||||||||||||
| F | 1 | 3 | 7 | 10 | 0 | |||||||||||||||
| G | 2 | 2 | 10 | 12 | 0 | |||||||||||||||
| Total resource load | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||||
| Resource available | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | |||||
Using your computations in the previous question, what is the new project duration?