Question: Please view the following and answer the multiple choice question Product A is made from 2 Bs and 1 C. Lead times for A, B,

Please view the following and answer the multiple choice question

Please view the following and answer the multiple

Product A is made from 2 Bs and 1 C. Lead times for A, B, and Care 2, 1, and 2 weeks respectively. Currently there are 5 As, 10 Bs and 10 Cs on hand. It is the start of week 1 now. The master schedule calls for 20 As at the start of week 5. When and how large of an order of C should be placed? A. start of week 1, 10 CS B. start of week 3, 20 Cs C. start of week 1, 20 Cs OD. start of week 3, 10 Cs O E. start of week 1,5 Cs