Question: pls answer asap C Problem 2: Draw the Network diagram and number the events in their proper sequence. Write all the possible path and determine

pls answer asap C Problem 2: Draw the Networkpls answer asap

C Problem 2: Draw the Network diagram and number the events in their proper sequence. Write all the possible path and determine also the Critical path of activities and the Duration of the project. Estimated time ACTIVITIES PRECEDES (days) a c, b 4 d 12 d i 2 b i 5 f 3 f 8 i end 9 h 1 h k 3 k end 12 RE 15