Question: pls Current Attempt in Progress Ayayai Company is preparing its manufacturing overhesd budget for 2022 Relevant data consist of the following Quarterly units production: Q19,400,Q211,800,Q313,200,Q15,600.
Current Attempt in Progress Ayayai Company is preparing its manufacturing overhesd budget for 2022 Relevant data consist of the following Quarterly units production: Q19,400,Q211,800,Q313,200,Q15,600. Direct labor: Labor required is 1 hour per unit. Variable overhead costs per direct labor hour Indirect materials $0.60, indirect labor $1.10; and maintenance $0.40. Fixed overhead costs per quarter: 5 upervisory salaries $41,500; depreciation $16,800, and maintenance $11,700 Prepare the manufacturing overhead budget for the year, showing quarterly data. (List variable costs before fixed costs.)