Question: Pls help me answer all MCQ. Thx a lot. Read the following figure to answer Q4 - 27: 18 D 10 M 11 8 9

Pls help me answer all MCQ. Thx a lot.
Read the following figure to answer Q4 - 27: 18 D 10 M 11 8 9 10 12 F 16 H2 4. Which of the following is the slack time of activity J? A. 0 B. 3 c. 11 D. 13 5. Determine the completion time of the project. A. 41 B. 42 C. 51 D. 52 6. Determine the critical path of the project. A. ADHIL B. ACMJL C. BFHIL D. BEHIL 7. What is the earliest start time of activity H? A. 17 B. 12 C. 21 D. 28Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock