Question: PLS HELP!! No Handwriting!!! Consider the given information in the following table of activities of the development of Stock Management System of Gulf Hypermarket. Assuming

PLS HELP!! No Handwriting!!!

Consider the given information in the following table of activities of the development of Stock Management System of Gulf Hypermarket. Assuming that the project team will work 5 working days in a week and that all tasks will start as soon as possible.

Task

Description

Duration

(days)

Predecessors

A

Requirements Analysis

5

--

B

System Design

15

A

C

Programing

25

B

D

Telecoms

15

B

E

Hardware Installation

30

B

F

Integration

10

C, D

G

System Testing

10

E, F

H

Training

5

G

I

Handover Project

5

H

(a). Draw the Activity on Node (AoN) network diagram.

(b). Find the critical path and write that path and its duration.

(c). If the activities D and E are delayed by 10 days, how it will impact on the project completion?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!