Question: PLS HELP!! No Handwriting!!! Consider the given information in the following table of activities of the development of Stock Management System of Gulf Hypermarket. Assuming
PLS HELP!! No Handwriting!!!
Consider the given information in the following table of activities of the development of Stock Management System of Gulf Hypermarket. Assuming that the project team will work 5 working days in a week and that all tasks will start as soon as possible.
| Task | Description | Duration (days) | Predecessors |
| A | Requirements Analysis | 5 | -- |
| B | System Design | 15 | A |
| C | Programing | 25 | B |
| D | Telecoms | 15 | B |
| E | Hardware Installation | 30 | B |
| F | Integration | 10 | C, D |
| G | System Testing | 10 | E, F |
| H | Training | 5 | G |
| I | Handover Project | 5 | H |
(a). Draw the Activity on Node (AoN) network diagram.
(b). Find the critical path and write that path and its duration.
(c). If the activities D and E are delayed by 10 days, how it will impact on the project completion?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts