Question: pls help solve question 3 Week Crew Size Yards Installed 1 2 3 4 5 6 3 4 2 72 92 50 69 52 2

pls help solve question 3
Week Crew Size Yards Installed 1 2 3 4 5 6 3 4 2 72 92 50 69 52 2 Compute the labor productivity for each of the weeks. On the basis of your calculations, what can you conclude about crew size and productivity? 3. Compute the multifactor productivity measure for each of the weeks shown for production of choc- olate bars. What do the productivity figures suggest? Assume 40-hour weeks and an hourly wage of $12. Overhead is 1.5 times weekly labor cost. Material cost is $6 per pound. Week Output (units) Workers Material (lbs) 30,000 450 33,600 470 3 32,200 460 480 4 35,400 4. A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts, Prior to buying the new equipment, the company used five workers, who produced an average of 80 carts per hour. Workers receive $10 per hour, and machine cost was $40 per hour. With the new 2 8Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock