Question: pls help with question 4,5,6 Use the data given in the following table to answer the next four problems. The table gives the order in

pls help with question 4,5,6
Use the data given in the following table to answer the next four problems. The table gives the order in which five jobs arrived in the production department; their processing times and due dates. Job Processing Time (Days) Due Date (Days) A 18 46 B 13 33 21 25 D 19 52 E 24 48 4. What is the average number of jobs in the system using the EDD rule? 5. What is the average tardiness using the FCFS rule? 6. What is the number of tardy jobs using SPT ruleStep by Step Solution