Question: Pls I need help ASAP 4. Perform a financial analysis for a project using the format provided in Figure 4-5. Assume that the projected costs

4. Perform a financial analysis for a project using the format provided in Figure 4-5. Assume that the projected costs and benefits for this project are spread over four years as follows: Estimated costs are $300,000 in Year 1 and $40,000 each year in Years 2,3 , and 4 . Estimated benefits are $0 in Year 1 and $120,000 each year in Years 2, 3, and 4 . Use a 7 percent discount rate, and round the discount factors to two decimal places. Create a spreadsheet or use the business case financials template on the Companion website to calculate and clearly display the NPV, ROI, and year in which payback occurs. In addition, write a para