Strategy as differentiated from tactics is:
Select one:
a. Based on cost only
b. Based on duration
c. Based on quality, only
d. Based on location, only
Clear my choice
Question 13
Not yet answered
Marked out of 1.0
Flag question
Question text
A queuing model where customer arrivals are at known intervals and the service time is also certain is a
Select one:
a. Stochastic model
b. General model
c. Probabilistic model
d. Deterministic model.
Clear my choice
Question 14
Not yet answered
Marked out of 1.0
Flag question
Question text
Competitive Strategies refer to :
Select one:
a. Cost reduction, only
b. Obtaining market information
c. Being better than the competitor
d. Not being in competition
Clear my choice
Question 15
Not yet answered
Marked out of 1.0
Flag question
Question text
Company website, ATM, self-service gas stations are examples of:
Select one:
a. Cost minimization
b. The self-service approach
c. The personal-attention approach
d. The production-line approach
Clear my choice
Question 16
Not yet answered
Marked out of 1.0
Flag question
Question text
Make-to-Order processes have
Select one:
a. Shortest delivery time
b. Longest delivery time
c. Medium delivery time
Clear my choice
Question 17
Not yet answered
Marked out of 1.0
Flag question
Question text
Trade off in Competitive Strategy can be :
Select one:
a. Between inventory and WIP
b. Between productivity and quality
c. Between flexibility and cost
d. Between efficiency and productivity
Clear my choice
Question 18
Not yet answered
Marked out of 1.0
Flag question
Question text
Following is a flow Chart representation of sequential workflow of the Project Tasks.
Select one:
a. Tree diagram
b. Chart map
c. Network diagram
d. Work flow matrix
Clear my choice
Question 19
Not yet answered
Marked out of 1.0
Flag question
Question text
Zen in Kaizen reveals-
Select one:
a. Better
b. Change
c. Least resources
d. Continuous
Clear my choice
Question 20
Not yet answered
Marked out of 1.0
Flag question
Question text
TO specify optimal combination of production rate, workforce level, and inventory on hand is called
Select one:
a. Demand Management
b. Aggregate Operations Plan
c. Master Production Schedule
d. Materials Requirement Planning