Question: plz thx You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and

You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. Calculate the free slack and total slack for all noncritical activities There is total slack on activities B,D,E,G,H, and J and free slack on activities H and J. Calculate the free slack and total slack for all noncritical activities There is total slack on activities B, D, E, G, H, and J and free slack on activities H and J. V How sensitive is the network schedule? Not very sensitive. There is a single dominant critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
