Question: PM . 5 7 The activities needed to develop a new software application are listed in the following table with the activity times and their
PM The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:
Activity Duration weeks Immediate Predecessors
A
B A
C A
D A
E A
F BC
G DE
H FG
What is the overall duration of the project in weeks
Number
weeks
What is the earliest week you could start activity FWrite the week number in the field below.
Number
What is the earliest week you could finish activity G
Number
What is the latest week you could start activity C
Number
What is the latest week you could finish activity B
Number
What is the slack time for activity G
Number
weeks
What would be the overall duration of the project if activity C were increased by weeks, from to weeks?
Number
weeks
What would be the overall duration of the project if activity G were increased by weeks, from to weeks?
Number
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock