Question: Question 2 PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order


Question 2 PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed: 8 points Number Help Activity | Duration (weeks) | Immediate Predecessor(s) A 5 How Did I Do? B A C 5 A D A E 5 A F 8 B,C G 13 DE H 7 F.G What is the overall duration of the project (in weeks)? Number weeks What is the earliest week you could start activity H? (Write the week number in the field below.) Number What is the earliest week you could finish activity G? Number What is the latest week you could start activity C? Number What is the latest week you could finish activity A? Number What is the slack time for activity C? Number weeks What would be the overall duration of the project if activity C were increased by 4 weeks, from 5 to 9 weeks? Number weeks What would be the overall duration of the project if activity E were increased by 5 weeks, from 5 to 10 weeks? Number weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
