Question: PM . 6 1 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 65 $1,000 $1,200-
B 53 $400 $600-
C 65 $400 $625-
D 53 $750 $1,050 A
E 63 $1,350 $3,150 C
F 32 $675 $775 B
What is the duration of the project (in weeks)?
Nmero
What is the target duration of the project (after crashing the project)?
Nmero
By how many weeks should activity A be crashed?
Nmero
By how many weeks should activity B be crashed?
Nmero
By how many weeks should activity C be crashed?
Nmero
By how many weeks should activity D be crashed?
Nmero
By how many weeks should activity E be crashed?
Nmero
By how many weeks should activity F be crashed?
Nmero
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)
15150PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he
wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
 PM.61 Rob Smith is managing a small project at Boston University.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!