Question: PM . 6 1 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the
PM Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity Normal Time weeks Crashed Time weeks Normal Cost Crashed Cost Predecessors
A $ $
B $ $
C $ $
D $ $ A
E $ $ C
F $ $ B
ALL ARE CORRECT OTHER THAN THE LAST QUESTION I NEED HELP WITH THAT ONE.
What is the duration of the project in weeks
What is the target duration of the project after crashing the project
By how many weeks should activity A be crashed?
By how many weeks should activity B be crashed?
By how many weeks should activity C be crashed?
By how many weeks should activity D be crashed?
By how many weeks should activity E be crashed?
By how many weeks should activity F be crashed?
What is the total cost of crashing the project weeks just the additional cost, not total project costDisplay your answer to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock