Question: PM . 6 6 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his

PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 32 $1,000 $3,300-
B 65 $2,200 $2,460-
C 43 $1,400 $2,500-
D 73 $2,100 $2,600 A
E 63 $1,650 $2,250 B
F 32 $4,100 $5,460 C
G 42 $1,600 $2,100 D, E
What is the overall duration of the project?
16
Which of the following activities has the lowest crash cost per week?
C
D
E
A
Which of the following activities has the highest crash cost per week?
B
C
G
F
If you wanted to shorten the overall duration of the project, which activity should you crash first?
C
B
A
E
D
What is the total cost of crashing the project from its current duration down to 13 weeks?
Number
Incorrect
Your Answer: 700
What is the total cost of crashing the project from its original duration to 11 weeks?
Number
Incorrect
Your Answer: 510
Incor

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!