Question: PM592 Week 5 Earned Value Analysis Graded Assignment Problem #1 Your project has four activities. Below is the current status of each activity. Task A

PM592 Week 5 Earned Value Analysis Graded Assignment Problem #1 Your project has four activities. Below is the current status of each activity. Task A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule. Task B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000. Task C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000. Task D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points) PV AC EV Task A B C D Project 2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project? (15 points) Task A B C D Project SV CV SPI CPI 3. Assess the project performance to date? Do you get to have the celebration? (5 points) PM592 Week 5 Earned Value Analysis Graded Assignment Problem #2 Your project has four activities. Below is the current status of each activity. Task A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule. Task B is at the end of week 2 of a planned 4-week effort. It is 65% complete. It was to cost $190,000 when finished. Its costs to date are $150,000. Task C is finished. It finished 2 weeks late. It cost $200,000. And it was planned to have cost $250,000. Task D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points) Task A B C D Project PV AC EV 2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project? (15 points) SV CV SPI CPI Task A B C D Project 3. What is your assessment of the project at this time? (5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!