Question: PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 5 3 $900 $1,500 -
B 6 5 $400 $450 -
C 6 5 $600 $825 -
D 3 2 $850 $1,050 A
E 6 3 $1,350 $2,700 C
F 5 3 $825 $1,225 B

What is the duration of the project (in weeks)?

What is the target duration of the project (after crashing the project)?

By how many weeks should activity A be crashed?

By how many weeks should activity B be crashed?

By how many weeks should activity C be crashed?

By how many weeks should activity D be crashed?

By how many weeks should activity E be crashed?

By how many weeks should activity F be crashed?

What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!