Question: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After
PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:

What is the overall duration of the project? Which of the following activities has the lowest crash cost per week? D C A E Which of the following activities has the highest crash cost per week? C G F B If you wanted to shorten the overall duration of the project, which activity should you crash first? B D A E C What is the total cost of crashing the project from its current duration down to 11 weeks