Question: Pmoblem 2 A 4 . 0 - m thick fill is to be built of a soll with a thit weight of 2 0 .

Pmoblem 2
A 4.0-m thick fill is to be built of a soll with a thit weight of 20.1kNm3. The underlying snils are as shown in the figare. Consolidation tests were performed at Points A and B, with the following results:
\table[[Sample,C.,Cr,eo,d'c],[A,0.59,0.19,190,75],[B,0.37,0.14,121,100]]
The silty sand is normally consolidated. Deteraine the ultimate consolidation settlement due to the weight of this fill.
Pmoblem 2 A 4 . 0 - m thick fill is to be built