Question: points eBookHintPrintReferencesCheck my workCheck My Work button is now enabledItem 7 Problem 5 - 7 ( Algo ) Williams Motor Manufacturing assembles small motors for

points
eBookHintPrintReferencesCheck my workCheck My Work button is now enabledItem 7
Problem 5-7(Algo)
Williams Motor Manufacturing assembles small motors for sale to major appliance manufacturers around the world. Average demand for its best-selling motor is 525 units per day. The assembly line operates continuously during a single 8-hour shift. The tasks required, task times, and precedence relationships are:
Task Time (seconds) Predecessors
A 14
B 24
C 21
D 26 A
E 16 C
F 36 B,D
G 24 E
H 28 F,G
I 18 H
pictureClick here for the Excel Data File
What is the takt time?
What is the theoretical number of workstations?
Assign the tasks to the workstations to balance the line using the longest operating time rule.
What is the efficiency of the balanced line?
If demand increased to 625 motors per day, what would be the new takt time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!