Question: ( Pr . 8 . 1 4 and 8 . 1 6 ) For the clay layer shown below, a ) Determine the average stress

(Pr.8.14 and 8.16) For the clay layer shown below,
a) Determine the average stress increase in the clay layer below
the center of the foundation due to the net foundation load of
900 kN. Use 2:1 method to find average stress increase in the
clay layer.
b) Estimate the consolidation settlement of the clay layer based
on the average stress increase in the clay layer.