Question: Practice Problems: Layout and Assembly 1. An assembly line with 17 tasks in series is to be balanced. The longest task is 2.4 minutes and

Practice Problems: Layout and Assembly 1. An assembly line with 17 tasks in series is to be balanced. The longest task is 2.4 minutes and total time for all tasks is 18 minutes. The line will operate 450 minutes per day. a) What are the minimum and maximum cycle times? (min:2.4; max: 18 mnts) b) What range of output is theoretically possibly (25 to 187.5) c) What are min number of workstations needed for max output? (8) d) What cycle time will provide an output of 125 units? (3.6 mnts) e) What output will result if cycle time is 9 minutes? (50)
 Practice Problems: Layout and Assembly 1. An assembly line with 17

1. An assembly line with 17 tasks in series is to be balanced. The longest task is 2.4 minutes and total time for all tasks is 18 minutes. The line will operate 450 minutes per day. a) What are the minimum and maximum cycle times? (min:2.4; max: 18mnts ) b) What range of output is theoretically possibly ( 25 to 187.5) c) What are min number of workstations needed for max output? (8) d) What cycle time will provide an output of 125 units? (3.6mnts) e) What output will result if cycle time is 9 minutes? (50)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!