Question: Practice Question Question 1 a ( 5 Points ) : Given the following activities and precedences, draw an AON diagram: Question 1 b ( 9
Practice Question
Question Points: Given the following activities and precedences, draw an AON
diagram:
Question b Points: Given the estimated activity times below and the network
above:
a What is the critical path?
b How long will it take to complete this project?
c Can activity be delayed without delaying the completion of the project? If so
how many days?
Question c Points: what is the probability that the project will be completed within
based on the path with the longest expected time:
a days?
b days?
c days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
