Practice Task 3 Task Predecessors Time Nor Time Crash Cost Nor Cos: Crash 1 2 6 8 3 5 6 91 B. 7 4 5 10 IC 2 1 8 9 D 8 12 2 B 3 E 11 F C 9 3 5 8 B 6 9 7 1 2 7 3 8 D.E 6 7 6 5 J 3 9 K FJ 6 4 3 2 F.H.J.I 1. Draw the network (A0A) 2. Identify the critical path 3. Calculate the cost slopes for the activities 4. Find 3 days of time savings in the most efficient manner