Question: Precedence table for a project is given as follows: Activity A Pre-requisite Duration 4 B C 75 D A E B 63 F C
Precedence table for a project is given as follows: Activity A Pre-requisite Duration 4 B C 75 D A E B 63 F C G D,E H G, F 143 11 Determine the earliest start time (EST), latest start time (LST), earliest finishing time (EFT) and latest finishing time (LFT). [6 marks]