Question: Precedence table for a project is given as follows: Activity A Pre-requisite Duration 4 B C 75 D A E B 63 F C

Precedence table for a project is given as follows: Activity A Pre-requisite

Precedence table for a project is given as follows: Activity A Pre-requisite Duration 4 B C 75 D A E B 63 F C G D,E H G, F 143 11 Determine the earliest start time (EST), latest start time (LST), earliest finishing time (EFT) and latest finishing time (LFT). [6 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!