Question: preceding activities activity duration A 10 B 4 8 B 6 8 I 5 - IT mo 10 AD 2 G 4 J 10 DF,

preceding activities activity duration A 10 B 4 8

preceding activities activity duration A 10 B 4 8 B 6 8 I 5 - IT mo 10 AD 2 G 4 J 10 DF, 1 A project consists of ten activities A-J. The duration (in days) of each activity, and the activities preceding of them are given in the table. a. Construct activity network diagram for this project. b. Find the critical path in this activity network. (10 Marks) (Non-anonymous question O) *

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!