Question: PRECEDING ACTIVITY ESTIMATE IN DAYS 0 6 5 3 3 ACTIVTY Start C D G B E H F End Start A D G D

PRECEDING ACTIVITY ESTIMATE IN DAYS 0 6 5 3 3

PRECEDING ACTIVITY ESTIMATE IN DAYS 0 6 5 3 3 ACTIVTY Start C D G B E H F End Start A D G D G E H,B,F 3 7 N 4 7 0 Using the following key ES Duration | EF Activity LS Float LF Determine, a) The critical path b) The float for activity D, F and H