Use the data in this table to answer the questions that follow: Activity Preceding Activity Estimate in
Fantastic news! We've Found the answer you've been seeking!
Question:
Use the data in this table to answer the questions that follow:
Activity
Preceding Activity
Estimate in Months
Start
D
Start
A
Start
F
D A
E
D
G
FE
B
F
H
G
C
H
End
C B
What is the duration of the critical path?
Posted Date: