Question: PREDECESSOR(S) 3 days TASK NAME NORMAL COST CRASH COST NORMAL DURATION A S 3,130.00 $ 3,430.00 1 days B S 1,313.00 $ 1,510.00 2 days

PREDECESSOR(S) 3 days TASK NAME NORMAL COST CRASH

PREDECESSOR(S) 3 days TASK NAME NORMAL COST CRASH COST NORMAL DURATION A S 3,130.00 $ 3,430.00 1 days B S 1,313.00 $ 1,510.00 2 days C $ 1,982.00 $ 1,281.00 D S 2,568.00 $ 1.391.00 5 days E S 2.428.00 $ 3.545.00 6 days 1 $ 2,506.00 $ 3.158.00 7 days G $ 1.445.00 $ 3.165.00 2 days H $ 783.00 $ 1.472.00 7 days J $ 1.200.00 $ 1.400.00 CRASH DURATION I Days I Days 2 Days 2 Days 2 Days 6 Days 1 Days 6 Days 6 1 Days A B A, D CE F. G H 2 days Daily indirect cost $ 650.00 QUESTION: CRASH THE ABOVE GIVEN PROJECT IN A WAY TO DETERMINE A DIRECT, INDIRECT, AND TOTAL COST FOR EACH POSSIBLE DURATION (UNTIL IT IS NOT CRASHABLE) FILL OUT THE TABLE GIVEN BELOW WITH THE CRASHING SOLUTION ALL CRISHABLE ACTIVITIES CAN BE CRASHED PER DAY GRADING RUBRIC O DETERMINE THE PATHS (4 PTS) O PATH DURATIONS, AND CRITICAL PATH(S) (5 PTS) o CALCULATE EACH POSSIBLE DURATION, DIRECT, INDIRECT COSTS, AND ACTIVITIES TO CRASH ON THE TABLE BELOW (11 PTS) O DRAW A GRAPHIC OF DIRECT INDIRECT AND TOTAL COSTS (X-AXIS TO SHOW DAYS, Y-AXTS TO SHOW S) (3 PTS) , O IDENTIFY THE OPTIMUM PROJECT DURATION (2 PTS) 2 ) DURATION DIRECT COST IND. COST TOTAL COST ACTIVITIES CRASHED

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!