Question: You are a Program Manager at Technocat Software Development and your client has asked you to complete the following project in eight days. Task Predecessors
You are a
Program Manager
at
Technocat Software Development
and your client has asked you to complete the following project in eight days.
| Task | Predecessors | Normal Time | Crash Time | Normal Cost | Crash Cost |
| A | - | 4 days | 2 days | $300 | $500 |
| B | - | 3 days | 2 days | $300 | $550 |
| C | A,B | 2 days | 1 day | $700 | $900 |
| D | B | 3 days | 1 day | $300 | $900 |
| E | D | 3 days | 2 days | $250 | $500 |
| F | C | 4 days | 3 days | $400 | $700 |
| G | B | 7 days | 6 days | $500 | $600 |
Technocat Software Development
Duration:Based on Normal Task Times what is the current estimated duration of the project?
nothingdays
Budget:Based on Normal Task Times and Normal Costs, what is the current estimated project budget?
$nothing
(please round to the nearest whole dollar)
Crash Cost:What is the additional cost to "crash" the project to achieve a duration of eight days?
$nothing
(please round to the nearest whole dollar)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts