Question: - Predecessors Activity A B 1 C D 3 E 2,4 F Duration 3 days 4 days 5 days 8 days 4 days 5 days

- Predecessors Activity A B 1 C D 3 E 2,4 F

- Predecessors Activity A B 1 C D 3 E 2,4 F Duration 3 days 4 days 5 days 8 days 4 days 5 days 3 days 5 days 1 day 3 days 4 days 2 days 4 G 6,5 H 7 I 8,9 10 K 11 Points 20 15 Instructions: 1. Develop the network diagram. Remember to use terminators. 2. Calculate the ES, EF, LS & LF of each activity. 3. Calculate the total float for the project. 4. Write down the critical path and its duration. 5. Submit using PowerPoint. 5 10 50