Question: Predecessors Activity A B Duration day 3 AWAW Labour 2 3 2 A 5 3 D A A 4 mmmm 2 E F G BD

Predecessors Activity A B Duration day 3 AWAW

Predecessors Activity A B Duration day 3 AWAW Labour 2 3 2 A 5 3 D A A 4 mmmm 2 E F G BD CD E,F. 3 2 5 3 w Assuming that each activity needs the same type of resourcen fort he Project, whose information is given in the table; A) What is the resource requirement on the third day? B) What is the resource requirement on the third day after making the necessary resource smoothing