Question: Predecessors activity time most optimist most probable most pessimist variance A 15 B 50 C 30 D 3 E A 7 F B,C,D,E 6 G

Predecessors activity time most optimist most probable most pessimist variance
A 15
B 50
C 30
D 3
E A 7
F B,C,D,E 6
G F 1
H G 36
I H 6
J I 6
K I 32
L I 4
M J,K,L 3
N M 15
O M 18
P N,O 2
Q P 5

a) Based on the data provided (activity, predecessors, and activity time), establish the shortest completion time for the project (i.e. the critical path).

b) Let optimistic time be 75% of activity time, most probable 100%, and most pessimistic 200%, calculate the expected activities time.

c) Obtain the variance around each expected activity time.

d) Establish the new expected duration of the project (i.e. the critical path).

please complete in excel

thank you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!