Question: Problem 2 (10 points) Given the following network and activity time, what are: a. Activities on critical path? b. Project completion time? c. Slack for
Problem 2 (10 points)
Given the following network and activity time, what are:
a. Activities on critical path?
b. Project completion time?
c. Slack for activities D and F?
d. The variance of critical path?
e. The probability that the project will be completed in 27 days or less.
|
| Time Estimates (Days) | Immediate Predecessors | ||
| Activity | a | m | b |
|
| A | 5 | 8 | 17 | - |
| B | 7 | 10 | 13 | - |
| C | 3 | 5 | 7 | A |
| D | 1 | 3 | 5 | A |
| E | 4 | 6 | 8 | B, C |
| F | 3 | 3 | 3 | B, C |
| G | 3 | 4 | 5 | D, E |