Question: Problem 2 (10 points) Given the following network and activity time, what are: a. Activities on critical path? b. Project completion time? c. Slack for

Problem 2 (10 points)

Given the following network and activity time, what are:

a. Activities on critical path?

b. Project completion time?

c. Slack for activities D and F?

d. The variance of critical path?

e. The probability that the project will be completed in 27 days or less.

Time Estimates (Days)

Immediate Predecessors

Activity

a

m

b

A

5

8

17

-

B

7

10

13

-

C

3

5

7

A

D

1

3

5

A

E

4

6

8

B, C

F

3

3

3

B, C

G

3

4

5

D, E

Problem 2 (10 points) Given the following network

a. Problem 2 (10 points) Given the following network and activity time, what are: Activities on critical path? b. Project completion time? Slack for activities D and F? d. The variance of critical path? The probability that the project will be completed in 27 days or less. Time Estimates (Days) Immediate Predecessors c. e. Activity a m b . 5 8 17 B 7 10 13 3 5 7 D 1 3 5 A E 4 6 8 B, C F 3 3 3 B, C G 3 4 5 5 D, E 1 A B 1 32

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!