Question: Predecessors Optimistic Most Likely Pessimistic A N / A 1 2 3 B A 2 4 6 C A 2 5 8 D A 1

Predecessors
Optimistic
Most Likely
Pessimistic
A
N/A
1
2
3
B
A
2
4
6
C
A
2
5
8
D
A
1
1
1
AND
B, C
2
3
4
F
D
1
2
3
Q9. What is the probability the project will be completed in 8 weeks?
The 0.0451
The 0.0212
0.0514
0.0351