Question

1 Approved Answer

Prepare a line of balance schedule for a small contract of sixty (60) houses based on a rate of build of five (5) houses

Prepare a line of balance schedule for a small contract of sixty (60) houses based on a rate of build of five 

Prepare a line of balance schedule for a small contract of sixty (60) houses based on a rate of build of five (5) houses per week assuming a five-day (10 hrs per day) working week. A minimum buffer of three days should be assumed. The following table shows the activities together with the established labour-hours and optimum number of people for each activity. Activity A B C D E F 2 Labour required per unit 120 220 280 70 30 140 The sequence of operation is as follows: A hours Optimum gang size 5 4 6 2 4 2 3 1/ 5 E (a) Prepare a line of balance (LOB) diagram for the project. (b) Indicate the total project duration clearly. F 8

Step by Step Solution

3.59 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management and Cost Accounting

Authors: Colin Drury

10th edition

1473748873, 9781473748910 , 1473748917, 978-1473748873

More Books

Students also viewed these Programming questions

Question

Businesses that sell directly to final consumers

Answered: 1 week ago

Question

general journal

Answered: 1 week ago

Question

Explain the principles of delegation

Answered: 1 week ago

Question

State the importance of motivation

Answered: 1 week ago

Question

Discuss the various steps involved in the process of planning

Answered: 1 week ago

Question

What are the challenges associated with tunneling in urban areas?

Answered: 1 week ago

Question

What are the main differences between rigid and flexible pavements?

Answered: 1 week ago

Question

What do you suppose influences the last-minute swings of people?

Answered: 1 week ago