Question: Prepare a master production schedule with the information given as follows. The forecast for each week of am eight week schedule is 50 units. The
Prepare a master production schedule with the information given as follows. The forecast for each week of am eight week schedule is 50 units. The MPS rule is to schedule production if the projected on hand inventory would be negative without it. Customer orders are as follows. Production lot size is 75, safety stock is 10 and no beginning on hand inventory. Calculate available to promise (ATP) quantity for each period.
| Week | Customer Orders |
| 1 | 52 |
| 2 | 35 |
| 3 | 20 |
| 4 | 12 |
| Period |
|
|
|
|
|
|
|
|
| Forecast |
|
|
|
|
|
|
|
|
| Cust.Ord. |
|
|
|
|
|
|
|
|
| SS |
|
|
|
|
|
|
|
|
| Proj. OH |
|
|
|
|
|
|
|
|
| MPS |
|
|
|
|
|
|
|
|
| ATP |
|
|
|
|
|
|
|
|