Question: Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 75 units. The MPS rule is to schedule

 Prepare a master schedule given this information: The forecast for each

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 75 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Use a production lot size of 100 units and no beginning inventory. (In the ATP row, enter a value of O (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter " 0 " wherever required.)