Question: Expected task time: ES = Earliest Start = Max ( EF of all immediate predecessors ) EF = Earliest Finish = ES + Activity time

Expected task time:
ES = Earliest Start = Max (EF of all immediate predecessors)
EF = Earliest Finish = ES + Activity time
LF= Latest Finish = Min (LS of all immediate successors)
LS = Latest Start = LF Activity time
Slack = LS ES or Slack = LF EF
Using Table 4, type in the correct whole number for each tasks
expected task time (te)
earliest start time (ES)
earliest finish time (EF)
latest start time (LS)
latest finish time (LF), and
Type Yes or No in the space provided to indicate whether the task is a critical task.
NOTE: If you are unable to select any of the cells toward the right-hand side of the PERT Table, please click on a cell within the same row on the left-hand side of the table and use the 'Tab' key to tab over to the cell you would like to ed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!