Question: Expected task time: ES = Earliest Start = Max ( EF of all immediate predecessors ) EF = Earliest Finish = ES + Activity time
Expected task time:
ES Earliest Start Max EF of all immediate predecessors
EF Earliest Finish ES Activity time
LF Latest Finish Min LS of all immediate successors
LS Latest Start LF Activity time
Slack LS ES or Slack LF EF
Using Table type in the correct whole number for each tasks
expected task time te
earliest start time ES
earliest finish time EF
latest start time LS
latest finish time LF and
Type Yes or No in the space provided to indicate whether the task is a critical task.
NOTE: If you are unable to select any of the cells toward the righthand side of the PERT Table, please click on a cell within the same row on the lefthand side of the table and use the 'Tab' key to tab over to the cell you would like to ed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock